The construction process of PVC flooring

Writer: pvcflooring Time:2017-12-07 Source :China pvc flooring,
Primary coverage :The construction process of PVC flooring: Grass-roots treatment 1, wall, ceiling and doors and windows, such as the completion of the installation, clean the ground cleanliness. 2, remove the sand, oil pollution and remnants of the base surf

 The construction process of PVC flooring:

Grass-roots treatment
1, wall, ceiling and doors and windows, such as the completion of the installation, clean the ground cleanliness.
2, remove the sand, oil pollution and remnants of the base surface.
3, clean the ground dust and sand.
4. After the ground is thoroughly clean and clean, the interface agent is rolled evenly.

Self leveling construction
1, check whether the cement self leveling is in accordance with the relevant technical standards, such as the overdue self flow is not to be used.
2, will pour the proper amount into the dissolve device, according to the product description, the water will be diluted by clean water.
3, stirring until the cement self into the fluid matter.
4, the order of self leveling down on the ground, with the construction of scraper to scrape, tooth thickness of about 2-3mm.
5. No pedestrians and stacked articles are not allowed within 4 hours after the construction of self leveling.
Put the floor on the floor
1. According to the design pattern, the size of the floor, the size of the room, the partition and the location of the line.
2, at the grassroots level pop-up center cross line or diagonal, and parquet block pop-up line.
3, the edge of the wall line, lines must be clear and accurate.
4, the floor is paving before the line is dry, pre - spelled and numbered to the board.
Floor installation
1. First, wipe the ground floor with hair sweep or dry towel, clean the dust.
2. Apply the toothed scraper evenly on the base surface, paste the plate from the inside to the surface, and lay it up one or two times, then compacted with a roller or push plate.
3, the plate paving after, according to temperature judgment stick detergent dry clean, then, seam welding.
4, before welding, cut the adjacent two blocks into V groove, the electrode is made of the same electrode and the temperature of the hot air gun is 180 degrees, 250 degrees.
5, the electrode after cooling with the shovel will be higher than the surface excess welding cut smooth operation should be careful not to damage the floor surface of the shovel.

Related reading

Contact us
Contact
Contact us
I've been waiting for you here

TEL:15011133801

FAX:15810985180

NUB:15011133801

QQ:924254553,564129967

Email:924254553@qq.com

ADD:Courtyard No. 3, autonomous city, Boda Road, Chaoyang District,

[UP] 
关于我们 产品中心 工程案例 地板新闻 帮助中心 工程经验 联系我们
Online Service

QQ Oline

QQ Oline

QQ Oline

CALL:
15011133801
QR code

Wechat

`